Floating a
260 ton concrete bridge every 15 minutes since
1992
.......................................................................................................................................................................................................................
.........................................................................................................................................................................................................................
Application:
Sun International,
a customer well known in the casino industry
required a safe and cost effective method for
making a bridge float and imitate an earth quake
for the theme of a ruined Earthquake devastated
"Lost City"
in the
mid African resort of the
Lost City, a theme Casino
in
Bophuthatswana.
Solution:
After carefully surveying
the site and meeting with the customer, a concept
was established and agreed. Using a team of
three sub contract Companies for
pneumatics,
Fabrication and installation. The construction
work took a total of 4 months as the bridge
structure was already in place and needed to be
lifted using air bags and secured so that the
plumbing and the 18 "Large" Air Casters could be
fitted in place. the entire structure is held in
place by
18 Firestone Rail Car Suspension type actuators
with a plc control to automate the system,
Finally this is powered by a large
Atlas Copco Compressor.
Concept, Design and installation was completed by
Pat White and a team of lateral thinking
pneumatics, electronic and fabrication engineers
that worked at the fabulous resort for 6 months
to achieve an effect that runs to this day since
1992 - INNOVATIVE ENGINEERING IN MOTION !
Benefits: